> Nuclear power works too, it’s clean and low carbon impact.
You want an AI company to invest in a project that takes decades to complete? What are the chances they're around when it completes and what powers their datacenters while that takes place
Just to be pedantic: The median construction time is 7 years. With very slow planning, it is a decade, not decades. It can be done faster though.
Our power consumption won't be going down, and it generally wouldn't be the AI company itself running the project but the electricity companies that earn money supplying power that see dollar signs in all that extra electricity consumption.
Even if the AI companies all die, our global electricity consumption will keep going up margins will be better than the retired plants, so it's a good investment regardless.
I think you should look up actual construction times on reactors in developed countries. Be VERY happy if you can do it in less than 15 years.
> Even if the AI companies all die, our global electricity consumption will keep going up margins will be better than the retired plants, so it's a good investment regardless
If the company putting up the money goes bankrupt, what happens to the project? Maybe it's picked up by someone else?
I think AI companies should try to make it to 2030, my guess is at least a few of them won't make it. Don't commit to projects that won't even complete in the 2030s
I think you should look that up. I was even being conservative: Korea and China seems to be managing consistently around the 6 year time scale, while Japan has done it in less than four years from construction start till operation.
Granted, the US would have to import professionals to do it at that speed, and politicians will of course try to hinder the process with endless bureaucracy as their sponsors would rather sell fossil fuels...
> If the company putting up the money goes bankrupt, what happens to the project?
If people didn't start such medium-length projects out of fear of hypothetical future bankruptcy, there would never have been any infrastructure projects. Investors do not worry about them going bankrupt, they worry about losing momentum and would generally rather light money on fire than stagnate. We live in a time where business people start space programs out of bloody boredom.
However, what happens in these cases is just that other investors flock the carcass and takes over for cheap, allowing them to reap the benefits without having to have footed the whole bill themselves. Bankruptcy is not closure for a company, but a restructuring often under new ownership.
The only realistic scenario where such project would be dropped is if the world situation changed enough such that it would no longer be considered profitable to complete, such as due to other technology massively leapfrogging it to the point where investing in that from scratch is better than continuing investment, or demand being entirely gone such that the finished plant would be unproductive. Otherwise the project would at most change hands until it was operational.
(Particular AI companies making it to 2030 is not really that important when it is electricity producers making these investments and running these projects to earn money from AI companies, EV charging, heatpumps, etc.)
Finland, Olkiluoto, license application 2000, construction started in 2005, planned operation in 2010, actual operation 2023.
France Flammanville 3, construction started in 2007, planned operation in 2012, actual operation 2024, so 17 years
Hinkley point UK, construction began 2017 projected commissioning is in 2029/2030.
Vogtle USA, permits 2006, construction started 2013, operation 2023/2024.
South Korea, shin kori 3 and 4 took 7 and 10 years. And those aren't new designs.
Japan, the newest commissioned reactor is from 1997? Sure, France built really fast in the 80s... Different requirements/rules/public opinion.
And this is all from the start of construction. The beginning of the project is actually waaaay before that.
Please send me some links when you've done your research to prove me wrong. And yes, I did leave out china because I don't see the us building a Chinese design reactor... And even if that was possible it wouldn't meet us standards so you can effectively start over.
> If people didn't start such medium-length projects out of fear of hypothetical future bankruptcy, there would never have been any infrastructure projects.
And who finances that? Not banks by themselves, governments always have to give out some loan guarantees or favorable treatment. No private investor can deal with that amount of risk. So the bureaucracy that you speak of, without it no nuclear plant would exist.
So why don't you point me to a commercial nuclear power plant that was privately funded without loan guarantees by a government and all of that.
> We live in a time where business people start space programs out of bloody boredom.
So if you're referring to SpaceX, no Musk started that to make life multi planetary. And he understood that no one will finance that so the company needs to first make money to finance that mars shot.
Bezos I'm less familiar with but I know he has a collection of space artifacts so I think it's an interest of his and he probably wants to show he can do what musk can.
Google/MS/Meta will be around, probably. The other AI companies? Certainly not all of them.
I wouldn't rule out the current expenditure on AI to be a risk to the big players either. They're putting so much money in this. And with all the off balance sheet tricks that are happening now it'll be hard to know the real exposure.
You want an AI company to invest in a project that takes decades to complete? What are the chances they're around when it completes and what powers their datacenters while that takes place